On a well-run large job, there is one place you go for the sheets that govern the work today. Yesterday's set is still on file, marked as superseded, so you can see what changed. That is not about liking tidy folders. It is how a general contractor keeps the superintendent, the sub, and the person in the office from holding three different "latest" sets.
I kept that kind of file at Mortenson Construction, on a mission-critical data center project, including the Procore onboarding. The platform was how we enforced the rule, but the rule is older than the software: one current set, one date, one place. You can borrow it without buying the platform.
What "current" actually has to mean
A drawing is current only if somebody made it current. A PDF on a phone, a roll in the truck, and a set on the trailer table are not automatically the same thing, even if each one was "the latest" when it was printed or downloaded.
The current set is the official issued drawings that govern today's work, plus any closed RFIs, ASIs, or sketches that change those drawings and have been posted where the field will see them. Everything those sheets replaced belongs in a superseded folder, not in the same pile, and not still clipped to a board in the job trailer.
Two habits make the rule real:
- When a new revision arrives, the new PDF goes into the current folder, and the old one moves to superseded the same day. Nobody "cleans up later." "Later" is how last week's set stays in the truck.
- If a sheet is not in the current folder, do not build from it. If a superintendent cannot open that folder on a phone in the sun, the official set will quietly move back to a private stash of PDFs, and you will have lost the rule.
Free: the Built On Record Job File Kit — logs, checklists, and a folder tree
Unsubscribe any time. Privacy
That is the cheapest insurance I know against building last week's design.
Why the big GCs will not leave this to chance
Revisions happen on jobs of every size. An architect issues a new floor plan. A structural bulletin shifts an opening. A civil revision moves a sleeve or a cleanout. None of that is unusual. What gets expensive is a crew doing careful work from the wrong sheet.
You already know the shape of the cost: a wall built to old dimensions, a door opening that no longer matches the hardware, then labor, material, and a conversation about who pays. I walk through two versions of this miss in "Built Off Last Week's Sheet" and "Two 'Current' Sets on the Same Job."
Large contractors insist on one current set because they have paid for those misses often enough to staff a person and buy software to prevent them. The software is not magic. Underneath, it is a locked folder with a date and a distribution record. You can run a version of that with Google Drive or Dropbox if only a short list of people can replace the drawings.
A rule a superintendent can keep
You do not need a document control department to enforce this. You need a shared job folder, a current-drawings folder that is obvious, a superseded folder next to it, and a naming convention that starts with the date. A one-page note in the root should say the rule: if it is not in this folder, do not build from it.
Review the current set when new sheets arrive, and again the afternoon before a pour, a cover-up, or an inspection, not at 4 a.m. when the trucks are already on the way. Arizona heat makes that timing real. A companion article, "A Procore-Level Job File With Google Drive (or Dropbox) and a Spreadsheet," gives a folder tree you can copy. The current set still has to be a human rule.
If the revisions are coming faster than the file
Some jobs will hold with a clean folder and a superintendent who will move sheets when they arrive. Others will not, whether because revisions are coming fast or because the field has no hours left for paperwork.
If that sounds like your job, I can set up the job file, keep the current set honest on a retainer, or prepare closeout. If you want a second set of eyes, show me where your drawings live now. The plans in the truck are only current if somebody made them current.
If you want help, not just a checklist
Some jobs run fine on a clean file and a superintendent who gives the log fifteen minutes twice a week. Others do not: revisions are moving fast, closeout is already behind, or the field simply has no hours left for paperwork.
That is where I come in. I set up the job file, run the logs on a retainer, or prepare closeout before the scramble starts. Your files stay yours, and there is no software contract to sign.
A job-file kit you can use this week
Free logs and checklists for RFIs, submittals, dailies, changes, transmittals, pay apps, warranties, and closeout, plus a folder tree to keep them in. Sent by email, with an occasional practical note after that.
Free. Unsubscribe any time. Privacy