Inspection paper is easy to treat as someone else’s problem until a final, a closeout package, or a later question depends on it. Then the superintendent is looking for a passed inspection in a text thread, a correction notice on a paper card in the truck, or a portal login that belonged to a person who has left the job.
This is not legal advice, and it is not a guide to any one jurisdiction’s building code. Arizona cities and counties run their own permitting and inspection processes. Phoenix, Mesa, Scottsdale, Tucson, unincorporated county areas, and the rest each have their own portals, card systems, and sign-off habits. I am not going to list ordinance numbers or treat one city’s process as everyone’s. The document control habit is the same in all of them: whatever official record the inspector left you, file a copy in the job, named and dated, where more than one person can find it.
What is worth keeping
Free: the Built On Record Job File Kit — logs, checklists, and a folder tree
Unsubscribe any time. Privacy
For each inspection that matters to the work, try to keep:
- The request or scheduling confirmation, if you have one
- The result: passed, failed, partial, or cancelled, with the date
- The correction notice or comment list, if the inspection failed or was qualified
- The follow-up result when it is re-inspected
- Final or certificate-related documents when they are issued
- Photos of the work as it was presented, especially if something will be covered
Name the files so they sort: YYYY-MM-DD_Job_Inspection_TradeOrType_PassOrFail. Keep them in a clear folder (many jobs use one under quality or closeout, or a dedicated Inspections folder), not in a personal email. If the city uses a portal, download or print the result when you can. Portals change, and logins go away.
A short process after every inspection
- File the official result the same day, even if it failed.
- If there are corrections, add them to a punch or corrections list with a trade and a due date, and take photos of the condition.
- When it passes on a later visit, file that result next to the fail. Do not overwrite it. The history is the record.
- Point the daily report at the inspection: who came, what was inspected, what happened. See Daily Report Template.
- Before a cover-up, a ceiling close, or a pour that hides work, confirm the required inspection is in the file, not just “remembered.”
Closeout and the last missing card
Final sign-offs and outstanding correction items belong on the closeout checklist, not in a last-week hunt. If a document only exists in a city portal, get a copy into the job file before the person who had the login leaves. When the habit will not hold on its own, I can set up that folder, keep incoming inspection paper filed on a retainer, or include it in closeout prep. I do not schedule inspections, and I do not deal with the city for you. The files stay yours.
If you want help, not just a checklist
Some jobs run fine on a clean file and a superintendent who gives the log fifteen minutes twice a week. Others do not: revisions are moving fast, closeout is already behind, or the field simply has no hours left for paperwork.
That is where I come in. I set up the job file, run the logs on a retainer, or prepare closeout before the scramble starts. Your files stay yours, and there is no software contract to sign.
A job-file kit you can use this week
Free logs and checklists for RFIs, submittals, dailies, changes, transmittals, pay apps, warranties, and closeout, plus a folder tree to keep them in. Sent by email, with an occasional practical note after that.
Free. Unsubscribe any time. Privacy